When Can Contractors Work at the Shore? Summer Construction Rules in Jersey Shore Towns

If you’re planning a project on a shore house (new drainage, a stone parking pad, a cleanout, a teardown), when you do it matters as much as what you do. Several Jersey Shore towns have summer construction rules, and a few limit work all year. So if you book the job for the wrong week, the crew may legally be unable to start the machine. Here are the summer construction rules town by town.

Below are the rules we’ve checked in the town codes and official notices for shore towns in Monmouth and Ocean County, plus what they mean for scheduling. Almark Construction is a Middletown general contractor that does excavation, grading, cleanouts and hauling at the shore. So we check summer construction rules before every job.

The rules, town by town

Monmouth Beach to Deal

TownWhen the limits applyWhat’s restrictedSource
Monmouth BeachAll yearConstruction and demolition only 8 a.m. to 5 p.m. on weekdays and 9 a.m. to 3 p.m. on Saturdays. None on Sundays or federal holidays. Landscapers and other non-resident crews running power tools follow the same Saturday hours, with weekdays ending at 6 p.m. Emergency work excepted.Borough Code § 3-1.9 (Ord. O-03-22)
Long BranchAll yearConstruction, demolition, excavation and repair work only 7 a.m. to 6 p.m. on weekdays and 8 a.m. to 6 p.m. on Saturdays. None on Sundays. Emergencies excepted; homeowners doing their own repairs have separate hours.Ch. 235, Noise (§ 235-1A(9))
AllenhurstJune 30 to Labor Day, plus Thanksgiving and ChristmasNo building, construction, remodeling or repairs, and no power tools (sanders, saws, nail guns). Painting without power sanding or outside scaffolding, hand sanding, power-washing and regular landscaping are allowed. Homeowners can ask the Board of Commissioners for an emergency waiver.Developmental Regulations, Ch. 26 (work period limitation)
DealAll year; summer moratorium June 24 to the first Wednesday after Labor DayConstruction 8 a.m. to 7 p.m., Monday to Friday only. None on weekends or on New Year’s Day, Memorial Day, the Fourth of July, Labor Day, Thanksgiving or Christmas. During the moratorium, no building, construction, remodeling or repairs except emergency repairs and finishing work inside a fully enclosed building; machinery, dumpsters, portable toilets and debris off the lot by June 24.Ord. 2025-2 (Noise); Development Regulations § 30-100

Interlaken to Ocean Township

TownWhen the limits applyWhat’s restrictedSource
InterlakenAll yearBuilding work, including excavation and demolition, 8 a.m. to 8 p.m., Monday to Saturday. None on Sundays unless the Construction Official issues an emergency permit.Borough Code § 3-1.3
Loch ArbourAll yearBuilding, alteration and repair work, including excavation and demolition, only 7 a.m. to 6 p.m. on weekdays. Urgent work in the interest of public health and safety needs an emergency permit from the Building Inspector, who can also allow other hours. No summer moratorium found in what the village has posted.Ordinance 27, Noise (adopted 1960, as posted on the village website)
Asbury ParkAll yearEquipment for commercial construction, repair, alteration or demolition work can’t run on weekdays from 6 p.m. to 8 a.m., from 6 p.m. Saturday to 8 a.m. Monday, or on legal holidays. In practice: 8 a.m. to 6 p.m., Monday to Saturday. Emergency work excepted.City Code § 3-25.4(e), Noise
Neptune (incl. Ocean Grove)All year, with shorter summer Saturdays (Memorial Day to Labor Day)Heavy or power construction equipment only 8 a.m. to 7 p.m. Monday to Saturday, cut to 9 a.m. to 4 p.m. on summer Saturdays. None on Sundays, Memorial Day, Labor Day or the Fourth of July. Emergencies excepted with a permit.Township code § 3-2 (Noise), subsection 3-2.3

Bradley Beach to Spring Lake

TownWhen the limits applyWhat’s restrictedSource
Ocean Township (Oakhurst, Wanamassa, Wayside)All yearExcavation, grading, paving, demolition and other construction only 8 a.m. to 7 p.m. Monday to Saturday. No commercial construction on Sundays. Delivering, emptying or removing construction dumpsters and roll-offs follows the same hours. Residents doing work on their own property may also work Sundays, 9 a.m. to 6 p.m. Emergencies excepted with a permit.Township code § 3-3 (Noise), subsection 3-3.3g (Ord. No. 2406, 2023)
Bradley Beach6 p.m. on the Friday before Memorial Day to 8 a.m. on October 1Contractors can’t do noise-producing work (construction, landscaping, tree trimming) from Friday 6 p.m. to Monday 8 a.m., or on holidays. Emergencies excepted.Ord. 2023-09 (Ch. 310, Noise)
BrielleAll yearContractors’ construction, repair, alteration and demolition equipment only 7:30 a.m. to 6 p.m. on weekdays and 9:30 a.m. to 3 p.m. on Saturdays. None on Sundays. Some federal, state and county public projects are exempt.Borough Code § 3-1.9(d)
Spring Lake HeightsAll yearConstruction, alteration and excavation equipment that makes disturbing noise can’t run from 8 p.m. to 8 a.m. on weekdays or at any time on Sundays, unless the work is needed in the public interest.Revised General Ordinances, Ch. 3 noise section (Ord. No. 03-2012)
Spring LakeAll year; no Saturdays from Memorial Day weekend through September 30Equipment for commercial construction, repair, alteration or demolition work only 8 a.m. to 6 p.m. Monday to Friday, and 8 a.m. to 6 p.m. on Saturdays only from October 1 until the Saturday of Memorial Day weekend. No construction noise on Sundays, New Year’s Day, Good Friday, Memorial Day, the Fourth of July, Labor Day, Thanksgiving or Christmas.Ch. 250, Noise, § 250-8F (Ord. No. 2014-004)

Bay Head to Point Pleasant

TownWhen the limits applyWhat’s restrictedSource
Bay HeadAll yearContractors can do construction, excavation, demolition and landscaping only 8 a.m. to 6 p.m., Monday to Friday. None on Saturdays, Sundays, New Year’s Day, Memorial Day, the Fourth of July, Labor Day, Thanksgiving or Christmas. Owners and tenants doing their own work have separate weekend hours. Urgent work can be allowed by the Construction Official.Ch. 163, Noise
MantolokingAll year, plus no Saturdays from June 15 to September 15Commercial construction equipment only 8 a.m. to 6 p.m. on weekdays and Saturdays, never from 6 p.m. Saturday to 8 a.m. Monday. No construction on Sundays, New Year’s Day, Memorial Day, the Fourth of July, Labor Day, Thanksgiving or Christmas. From June 15 to September 15, no commercial construction on Saturdays at all.Borough noise ordinance (§ 3-1.3)
Point Pleasant BeachAll year (since May 2026)No set work hours found, but a construction debris rule for every job, homeowners included: remove debris before leaving the site, clean the site at least once a day, keep debris out of streets and storm drains, and put a filter on a nearby public storm drain before cutting or drilling. Fines up to $100 per violation per day.Ord. 2026-11, Borough Code § 12-5, adopted May 5, 2026
Point Pleasant (borough)All year (since March 2024)Outside (third-party) contractors only 8 a.m. to 6 p.m. on weekdays and 9 a.m. to 6 p.m. on Saturdays. No work on Sundays or federal holidays. Fines start at $1,000 per day per violation. The borough’s noise code sets the same weekday and Saturday hours for all construction and demolition and requires mufflers on equipment. Separately, builders have to give the Construction Official written proof of where and how construction debris was disposed of before the final inspection.Borough Code Ch. 8 (Ord. No. 2024-01, added Mar. 11, 2024); § 3-1.9(c) (Ord. No. 2021-01, amended 2024); § 8-1.4 (Ord. #92-60)

Lavallette to Harvey Cedars

TownWhen the limits applyWhat’s restrictedSource
LavalletteSaturdays and Sundays in the summer bathing season; also Memorial Day weekend, the Fourth of July and Labor DayConstruction, demolition and pile-driving equipment that breaks the noise code. Year-round, no such equipment from 6 p.m. to 8 a.m. Emergency work excepted.Ch. 43, § 43-7F (Ords. 2022-06 and 2022-17)
Seaside HeightsAll yearConstruction allowed 8 a.m. to 6 p.m. weekdays and 10 a.m. to 3 p.m. Saturdays. None on Sundays or federal holidays. Aimed at crews and heavy equipment, not homeowner DIY.Borough ordinance adopted July 2024, holiday amendment November 2024 (as reported by Shorebeat)
Beach HavenMemorial Day to Labor Day (summer hours); the rest applies all yearConstruction and demolition can’t start before 8 a.m. on summer weekdays (7 a.m. the rest of the year) and must stop at 6 p.m. Saturdays start at 9 a.m. No construction on Sundays, Thanksgiving or Christmas. Landscaping and masonry follow the same pattern.Ch. 134, Noise (§ 134-3, § 134-12)
Harvey CedarsSummer seasonA summer construction moratorium on “disruptive utility work and roadway construction activities.” The borough’s notice doesn’t list the dates or exceptions; the full text is at the Clerk’s office.Ord. 2026-013 (Ch. 19), adopted May 18, 2026

Rules also change, and other towns are working on their own. Belmar’s council, for example, asked staff in the summer of 2026 to draft a single ordinance limiting construction hours on weekends and holidays. If your town isn’t on this list, it doesn’t mean there’s no rule; it means we haven’t confirmed one. We call the borough before we schedule.

For state rules on wetlands, flood areas and stormwater, see the NJ Department of Environmental Protection.

What summer construction rules mean in practice

A “weekday-only” summer is a short summer. In Bradley Beach and Lavallette, summer weekends are off-limits. In Seaside Heights, Saturdays are cut to five hours and Sundays are out all year. Holidays fall on Mondays, so a holiday week can lose three days in a row. As a result, a job that takes a week in October can stretch over two in July.

Noise rules hit machine work first. These ordinances are written around loud equipment: excavators, skid steers, generators, saws, pile drivers. Digging a drainage trench, regrading a yard or loading debris with a machine is therefore exactly the kind of work they target. Quiet inside work is usually treated differently, but check the wording for your town.

Late starts matter for hauling. When a borough says work can’t start before 8 or 9 a.m., the truck and dump trailer don’t get there early either. Then add summer traffic on Route 35, Route 37 and the Causeway onto LBI. The first load of the day leaves later.

Parking is its own limit. Even where the code is silent, a dump trailer or roll-off can’t sit on a packed beach block for long in July. Also, many shore streets are permit-parking or metered in season.

Why fall and winter are the best time for shore site work

Our off-season checklist for shore rentals walks through what to do month by month, from fall cleanouts to spring inspections.

Summer construction rules: what we do at the shore

See our town pages for West Long Branch and Monmouth Beach, Asbury Park, Deal, Allenhurst and Interlaken, Belmar, Bradley Beach and Avon-by-the-Sea, Bay Head and Mantoloking, Long Branch, Neptune and Ocean Township, Seaside Heights, Seaside Park and Lavallette, and Long Beach Island.

Almark Construction LLC is bonded, NJ HIC #13VH14001400, and based at 1385 Highway 35 in Middletown. Call (732) 977-8388 to get your shore project on the fall or winter schedule.

Frequently asked questions

It depends on the town. Bradley Beach bans contractor noise from Friday 6 p.m. to Monday 8 a.m. from the Friday before Memorial Day to October 1, and Lavallette bans loud construction equipment on summer weekends. Seaside Heights limits Saturdays to 10 a.m. to 3 p.m. and bans Sunday construction all year. Farther north on the barrier island, Bay Head allows no contractor work on Saturdays or Sundays at any time of year, and Mantoloking allows no commercial construction on Saturdays from June 15 to September 15. In Monmouth County, Deal allows construction only Monday to Friday, all year, and Allenhurst allows no building, remodeling or repairs at all from June 30 to Labor Day.

Next door in Loch Arbour, building work, including excavation and demolition, is allowed only from 7 a.m. to 6 p.m. on weekdays, all year. Brielle allows contractors’ equipment on Saturdays only from 9:30 a.m. to 3 p.m., and not on Sundays, all year. Next door in Spring Lake, construction equipment can run on Saturdays only from October 1 until Memorial Day weekend, so summer Saturdays are out, and never on Sundays. In Spring Lake Heights, noisy construction and excavation equipment can’t run at any time on Sundays, though the borough code sets no separate Saturday limit.

No. Beach Haven’s noise code doesn’t allow construction or demolition work on Sundays, Thanksgiving or Christmas, and from Memorial Day to Labor Day weekday work can’t start before 8 a.m.

No. Seaside Heights’ rule applies year-round: 8 a.m. to 6 p.m. on weekdays, 10 a.m. to 3 p.m. on Saturdays. No construction on Sundays or federal holidays.

Between October and April. There are no summer limits, houses are empty, parking is easy, and sandy lots can usually be worked through the winter when the ground isn’t frozen or flooded.

No, not for normal construction. Asbury Park doesn’t allow commercial construction or demolition equipment from 6 p.m. Saturday to 8 a.m. Monday or on legal holidays. Long Branch doesn’t allow construction, demolition or excavation on Sundays. Neptune (including Ocean Grove) bars heavy construction equipment on Sundays, Memorial Day, Labor Day and the Fourth of July. Ocean Township doesn’t allow commercial construction on Sundays, and dumpster and roll-off drop-offs and pickups follow the same hours. Emergency work is handled by permit in each town.

Yes. We check the borough’s work hours and seasonal limits before we put a shore job on the calendar.

Call (732) 977-8388

Ready to get started?

Call the office at (732) 977-8388 or use the contact page. For site emergencies, call the 24/7 line at (848) 444-8100.

Leave a Reply

Your email address will not be published. Required fields are marked *