Trees in Manasquan
Manasquan's shade tree chapter (Chapter 23) regulates private trees on vacant lots, lots where the house has been demolished, and lots where the foundation is being enlarged by more than 500 square feet. On those lots, a tree over 6 inches in diameter that stands more than 15 feet from the new construction can't be removed unless an exemption applies, and removing one calls for a replacement tree or a payment into the borough's tree fund. Trees taken down in the six months before a construction permit application still count. Since February 2024 (Ord. No. 2414-24), a new home or an addition of 500 square feet or more also has to plant two shade trees on the property or pay into the fund. Cutting, pruning or removing trees along a street or in a borough park needs a written permit from the Shade Tree Commission.
Trees in Brielle
Brielle's Chapter 17, Protection of Natural Features (Ord. No. 1135), calls for an application to the Code Enforcement Officer before a street tree 2.5 inches or more in diameter, or another tree 6 inches or more, comes down, with replacement trees planted based on the size of the tree removed. Residents removing fewer than four trees per acre within five years are among the listed exemptions. Brielle also has a registration for anyone paid to do landscaping or tree removal in the borough (Ord. No. 1118, renewed each February 1), and its definition of landscaping includes removing shrubs and hedges. We check with the Municipal Clerk what applies to a clearing job before we book it.
Land disturbance permit in Spring Lake Heights
Spring Lake Heights' code requires a Land Disturbance Permit from the Construction Official before land is disturbed anywhere in the borough (Ord. No. 3-2001), and its definitions count clearing and grubbing as disturbance. The application includes a plot plan showing existing features, drainage and the proposed work, the borough engineer reviews it. The finished grade can't leave a slope steeper than 10 percent. The Construction Official for Spring Lake Heights works out of the shared construction office at 423 Warren Avenue in Spring Lake, which also serves Brielle. Ask that office whether your job needs the permit; we'll plan the clearing around it. We didn't find a separate tree removal chapter in Spring Lake Heights' online code, so check with the borough before any tree comes down.
Work hours
Brielle allows contractors' equipment only 7:30 a.m. to 6 p.m. on weekdays and 9:30 a.m. to 3 p.m. on Saturdays, and not on Sundays (Borough Code § 3-1.9(d)). Spring Lake Heights bars noisy construction and excavation equipment from 8 p.m. to 8 a.m. on weekdays and all day Sunday. In Manasquan, work that opens a borough street is limited to 8 a.m. to 6 p.m., Monday through Saturday, and the noise code keeps commercial construction and demolition equipment to 8 a.m. to 6 p.m., Monday to Saturday, with none on Sundays or legal holidays (§ 3-28). We schedule machine clearing inside each borough's hours.
Soil erosion
Disturbing more than 5,000 square feet generally needs a soil erosion plan certified by the Freehold Soil Conservation District, which covers Monmouth County. Most yard and lot clearing jobs here are far smaller.
Not in the Pinelands
None of the three boroughs is on the Pinelands Commission's list of towns with land in the Pinelands Area.
811
New Jersey requires a call to 811 at least three business days before digging. We make that call before any job that involves grubbing, digging or grading. 811 doesn't mark private lines, so show us any buried lines to a shed, garage, pool or sprinkler system.