A shed or storage container is only as good as what it sits on. Set it on bare ground and it settles, racks out of square, and the doors stop closing. The floor stays damp and rots. A level, compacted stone pad fixes all of that. It’s one of the most common small jobs we do with an excavator and skid steer. A good shed base is a level, compacted stone pad.
Here’s how a good pad goes in, how big to make it and what to ask your town before you start.
Step 1: Ask the town first
Shed rules in New Jersey depend on the size of the shed and on your town, and they’ve changed over the years. Two questions to ask your town’s zoning and construction offices before anything is built:
- Do I need a zoning permit? Many towns require one for any shed, mainly to check setbacks from property lines.
- Do I need a construction permit? Small sheds are often exempt, and larger ones aren’t.
Here’s one local example. Stafford Township in Ocean County says a shed of 200 square feet or less. No more than 10 feet tall, doesn’t need a construction permit but does need a zoning permit. It must be properly anchored to the ground. A shed of 201 square feet or more needs a construction permit, with plans showing the construction, foundation and anchoring. Its foundation must go below the frost line, which the township gives as 30 inches. Your town’s numbers may be different, so check.
Storage containers
Are their own question. Some towns treat a container as an accessory structure, some limit how long a temporary one can stay. Some don’t allow them in residential zones at all. Ask before you order one.
If your property is in a flood zone, ask about that too, since flood rules can affect what you can place and how it’s anchored.
In the Pinelands? Parts of 14 Ocean County towns are in the state Pinelands Area. A shed accessory to a single-family home doesn’t need a Pinelands Commission application, but clearing more than you need for it can be a violation. You still need the town’s permits. In the Pinelands? Check what you can clear without a Commission application.
Before any digging, New Jersey law requires a call to NJ One Call (811) so buried utility lines get marked.
Step 2: Pick the spot
A good spot is
- High and dry. Not in a low area where water collects, and not in the path of runoff
- Within the setbacks the town gave you
- Reachable. You'll want a clear path for a wheelbarrow, a mower or, for a container, the delivery truck
- Clear of buried lines. New Jersey requires a call to 811 at least three business days before digging. We make that call before every machine job
Step 3: Size the pad
Make the pad bigger than the shed, so rain dripping off the edges lands on stone instead of splashing mud onto the walls. A common rule of thumb is about a foot of extra stone on every side. A 10 × 12 shed gets roughly a 12 × 14 base.
For a storage container, the pad needs to support the container’s full footprint and the delivery. Ask the container company how they set it and what kind of surface they need.