Fill, topsoil and stone are sold by the cubic yard, or for stone, often by the ton. Order too little and the job stops halfway. Order too much and you’re paying for a pile that sits on the driveway. The math is simple once you know the formula. This guide walks through it with examples from the kinds of jobs we do around Monmouth, Ocean and Middlesex County. Here’s how to figure cubic yards of fill, topsoil or stone.
Cubic yards of fill: the formula
Cubic yards = length (ft) × width (ft) × depth (ft) ÷ 27
There are 27 cubic feet in a cubic yard (3 ft × 3 ft × 3 ft). The one step people miss is converting depth from inches to feet: divide inches by 12.
| Depth | In feet |
|---|---|
| 2 inches | 0.17 ft |
| 3 inches | 0.25 ft |
| 4 inches | 0.333 ft |
| 6 inches | 0.5 ft |
| 8 inches | 0.67 ft |
| 12 inches | 1 ft |
Before any digging, New Jersey law requires a call to NJ One Call (811) so buried utility lines get marked.
Example 1: Topsoil for a new lawn area
You regraded a 1,000 square foot area and want to spread 4 inches of topsoil before seeding.
1,000 sq ft × 0.333 ft ÷ 27 = about 12.3 cubic yards
For comparison, the Ocean County Soil Conservation District’s seeding guidance for construction sites calls for topsoil at least 5 inches deep. At 5 inches, the same area takes about 15.4 cubic yards. If you’re putting a lawn on a disturbed site, it’s worth going toward the deeper number.
Example 2: Fill for a low spot
A low corner of the yard, about 20 ft × 15 ft, sits an average of 8 inches below where it should be.
20 × 15 × 0.67 ÷ 27 = about 7.4 cubic yards of fill
Low spots are rarely the same depth everywhere, so measure the depth in several places and average them. Fill also settles, especially loose fill that isn’t compacted in layers, so plan for a little extra and expect a second, lighter topping later.
Example 3: Stone base for a paver patio
A 12 ft × 16 ft paver patio with a plan that calls for 6 inches of compacted stone base:
12 × 16 × 0.5 ÷ 27 = about 3.6 cubic yards of base stone
Stone compacts when it’s run with a plate compactor, so the loose amount you order needs to be more than the finished compacted depth. The paver manufacturer’s installation guide or your contractor will spell out the base depth for your soil and use. Don’t guess at it.
Example 4: Stone for a gravel driveway
A 100 ft × 10 ft driveway getting a 4-inch layer of fresh stone:
100 × 10 × 0.333 ÷ 27 = about 12.3 cubic yards
If you’re refreshing a driveway that already has a good base, 2 to 3 inches on top may be enough. A new driveway or one with soft spots needs more depth and proper base stone underneath.
Example 5: A drainage trench
A 30 ft stone trench, 3 ft deep and 6 inches wide:
30 × 3 × 0.5 ÷ 27 = about 1.7 cubic yards of clean stone
Narrow trenches add up quickly, and the soil that comes out of the trench (about the same volume) has to go somewhere. That’s where haul-away comes in.
Cubic yards vs tons
Suppliers often sell stone by the ton and soil by the yard. How many tons are in a cubic yard depends on the material and how wet it is, so ask your supplier for their conversion for the exact product you’re buying rather than using a number from the internet.
Don't forget what comes out
Every dig-out produces spoil, and every regrade can leave extra soil. A patio dig-out, a trench and a driveway rebuild can each produce a pile of soil you didn’t plan for. New Jersey has rules on where excess soil and fill can go, so it shouldn’t just get dumped somewhere.
Almark Construction is an NJ A-901 licensed hauler with our own dump trailers and roll-off dumpsters. Our own excavator and skid steer, run by our own operator, do the dig-out, spreading and grading. We figure the quantities as part of the quote, so you don’t have to.
Call (732) 977-8388 or (848) 444-8100 with the measurements or a few photos, or request a quote at www.almarkconstruction.com.
Almark Construction LLC · 1385 Highway 35, Suite 272, Middletown, NJ 07748 · NJ HIC #13VH14001400 · bonded
Related: Excavation and skid steer services · Site work
FAQ
How do I calculate cubic yards?
Multiply length by width by depth, all in feet, then divide by 27. Convert inches to feet by dividing by 12.
How much topsoil do I need for 1,000 square feet?
About 12.3 cubic yards at 4 inches deep, or about 15.4 cubic yards at 5 inches.
How many tons of stone are in a cubic yard?
It depends on the stone and how wet it is. Ask your supplier for the conversion for the exact product.
What do I do with the extra soil from a dig-out?
Have it hauled by a licensed hauler. New Jersey has rules on where excess soil and fill can go. We haul it as an NJ A-901 licensed hauler.
Call (732) 977-8388
Ready to get started?
Call the office at (732) 977-8388 or use the contact page. For site emergencies, call the 24/7 line at (848) 444-8100.