04 / Lot and land clearing
Check these before clearing
Overgrowth rules in Monroe. Monroe's code (Chapter 249) covers grass, weeds, brush and other plant growth on land along a township street. After the township gives notice, the owner, tenant or occupant has three days to remove it. If it isn't done, the Code Enforcement Officer can have it removed. The cost is certified, becomes a lien on the property and is added to the next tax bill. Violations can carry a fine of up to $1,000, up to 90 days in jail, or both, for each offense. Three days is short, so if you get a notice, call early.
Trees. Monroe requires a tree removal permit to take down a tree on a homeowner's property (Municipal Code Chapter 97, Tree Preservation. The township's Shade Tree Commission page lists a $35 fee for the first five trees, so check the current fee), and developers need permission before cutting trees for new development. Because we don't remove trees, we mark the ones that stay before we start and clear around them. If you plan to build, sort out any tree permit with the township first.
Soil erosion. Disturbing more than 5,000 square feet, including clearing and grading, generally needs a soil erosion and sediment control plan certified by the Freehold Soil Conservation District, which covers Monmouth and Middlesex counties. Most yard-size jobs fall well under that. Building one single-family home is exempt unless it's part of a larger subdivision or site plan.
811. New Jersey requires a call to 811 at least three business days before digging. We make that call before any job that involves grubbing, digging or grading. 811 doesn't mark private lines, so show us any buried lines to a shed, garage or sprinkler system.